Northwestern Corp. v. Dep’t of Pub. Serv. Regulation
This matter involved a challenge to the final order of the Montana Public Service Commission disallowing $1,419,427 in claimed excess electric regulation costs and adjusted energy efficiency savings calculations. NorthWestern Corporation - doing business as NorthWestern Energy, the Natural Resources Defense Council, and Human Resources Council, District XI appealed the Commission’s decision. The district court affirmed the Commission’s final order. The Supreme Court affirmed, holding (1) the Commission used the correct legal standard in reviewing NorthWestern’s claim for excess outage costs; and (2) the “free ridership” and “spillover” calculations adopted by the Commission were supported by substantial evidence. View "Northwestern Corp. v. Dep’t of Pub. Serv. Regulation" on Justia Law
T-Mobile W., LLC v. City & Cnty. of. San Francisco
Plaintiffs, “telephone corporations” require installation of wireless facilities, including antennas, transmitters, and power supplies, on existing utility poles in the city’s rights-of-way. In 2011, San Francisco adopted an ordinance, requiring Plaintiffs to obtain a permit before installing or modifying any wireless facility in the public right-of-way, citing the need “to regulate placement … that will diminish the City’s beauty.” The ordinance required a showing of technological or economic necessity and created three “Tiers” of facilities based on equipment size. It conditioned approval for Tiers II and III on aesthetic approval; locations designated “Planning Protected” or “Zoning Protected,” or “Park Protected,” triggered different aesthetic standards. Any Tier III facility required a finding that “a Tier II Facility is insufficient to meet the Applicant’s service needs.” “Any person” could protest tentative approval of a Tier III application. The trial court held that the modification provisions violated the Middle Class Tax Relief and Job Creation Act; provisions conditioning approval on economic or technological necessity, were preempted by section 7901. The aesthetics-based compatibility standards were not preempted. An amended ordinance, enacted in response, retained the basic permitting structure, but removed the size-based tiers, requiring compliance with aesthetics-based standards based on location. The court of appeal reversed, finding that the ordinance was not preempted. View "T-Mobile W., LLC v. City & Cnty. of. San Francisco" on Justia Law
MPS Merchant Serv. v. FERC
Petitioners seek review of FERC's determination that various energy companies committed tariff violations in California during the summer of 2000. As part of a deregulation program, California created two nonprofit entities: the California Power Exchange Corporation (“CalPX”) and the California Independent System Operator Corporation (“Cal-ISO”). Both entities were subject to FERC jurisdiction, with CalPX operating pursuant to a FERC-approved tariff and wholesale rate schedule. The Cal-ISO tariff comprehensively regulated California’s power markets, and incorporated the Market Monitoring and Information Protocol (“MMIP”), which set forth rules for identifying and protecting against abuses of market power. The court concluded that FERC’s determination that Shell, MPS, and Illinova (“sellers”) violated the Cal-ISO tariff and MMIP during the Summer Period was not arbitrary, capricious, or an abuse of discretion. In this case, FERC reasonably interpreted the Cal-ISO tariff and the MMIP according to the plain text of those documents. Therefore, the court rejected the sellers’ claims that the tariff and MMIP did not proscribe the practices identified by the agency. Furthermore, FERC’s interpretation of the Cal-ISO tariff and the MMIP finds support not only in text, but in policy as well. The court concluded that FERC reasonably interpreted the Cal-ISO tariff and the MMIP to prohibit the practices of False Export, False Load Scheduling and Anomalous Bidding. In addition, the agency reasonably concluded that the tariff and MMIP sufficed to put sellers on notice that such practices were not permitted. The court also concluded that FERC reasonably concluded that the sellers engaged during the Summer Period in the practices deemed tariff violations by the orders on review. Finally, the court concluded that FERC’s Summer Period determinations regarding APX and BP were not arbitrary, capricious, or an abuse of discretion. Accordingly, the court denied the petitions for review in part and dismissed in part. View "MPS Merchant Serv. v. FERC" on Justia Law
Cal. Pub. Utils. Comm’n v. Superior Court
Aguirre sought injunctive and declaratory relief against the California Public Utilities Commission (CPUC) for failing to comply with the Public Records Act (PRA), Government Code sections 6250-6276.48 The complaint alleged that the San Onofre Nuclear Generating Station was closed after it leaked radiation in 2012; that costs of the shutdown and loss due to the shutdown exceeded $4 billion; and that CPUC approved the owner assigning $3.3 billion of these costs to utility ratepayers during an ex parte meeting in Warsaw, Poland. Aguirre made PRA requests seeking the production of emails and other documents related to the CPUC’s investigation of the shutdown and the settlement and meetings. The superior court rejected CPUC’s motion to dismiss. The court of appeal agreed with CPUC. Public Utilities Code section 1759 bars the superior court from exercising jurisdiction over the suit. The duty to comply with the PRA is an “official duty” of the CPUC. A “writ of mandate in any court of competent jurisdiction” is one of the statutory means available to enforce the PRA (Gov. Code 6258), and a “writ of mandamus” may be brought against the CPUC in the Supreme Court or the Court of Appeal in appropriate cases under section 1759(b). View "Cal. Pub. Utils. Comm'n v. Superior Court" on Justia Law
Santiago-Ramos v. Autoridad de Energia Electrica de P.R.
Plaintiffs filed a class action suit on behalf of approximately 1.5 million Puerto Rican residents who are customers of Autoridad de Energia Electrica de Puerto Rico (PREPA), alleging that PREPA used a portion of its overall revenue to subsidize municipalities’ energy use. Plaintiffs claimed violations of the Takings Clause and their procedural due process rights because PREPA deprived them of their property interest in electricity and/or the funds they paid for electricity. The district court granted summary judgment for PREPA,concluding that Plaintiffs had not identified a valid property interest, that no taking had occurred, and that no valid procedural due process claim existed. The First Circuit affirmed on other grounds, holding that because Plaintiffs did not identify a valid property interest, they did not have standing to bring the takings and due process claims. View "Santiago-Ramos v. Autoridad de Energia Electrica de P.R." on Justia Law
ENGIE Gas & LNG LLC v. Dep’t of Pub. Utils.
The Department of Public Utilities issued an order determining that the plain language of Mass. Gen. Laws ch. 164, 94A provides the Department with the statutory authority to review and approve ratepayer-backed, long-term contracts entered into by electric distribution companies for additional natural gas pipeline capacity in the Commonwealth. Plaintiffs filed separate petitions asking that the order be set aside on the ground that it was based on an erroneous interpretation of law. The Supreme Judicial Court vacated the Department’s order, holding (1) the order of the Department is a properly promulgated rule or regulation; but (2) the order is invalid in light of the statutory language and purpose of section 94A, as amended by the 1997 Restructuring Act, because it would undermine the main objectives of the Act. View "ENGIE Gas & LNG LLC v. Dep’t of Pub. Utils." on Justia Law
El Paso Electric Co. v. FERC
This case concerns a scheme of planning, cost allocation, and regulation imposed by FERC on EP Electric and the Intervenor electricity providers. EP Electric appealed from three decisions in which the Commission reviewed and required revisions to certain compliance filing that EP Electric and other utilities filed with FERC pursuant to Order No. 1000. Order No. 1000 is FERC’s rule regulating regional transmission planning and cost allocation by public utilities, also known as “jurisdictional utilities.” The court concluded that the Commission acted arbitrarily and capriciously in its mandates regarding the role of non-jurisdictional utilities in cost allocation and regional planning in the WestConnect region. Therefore, the court granted the petitions for review in part. The court vacated the Commission's Compliance Orders on these issues for further explanation and proceedings. The court denied review or dismissed in all other respects because EP Electric's remaining challenges to FERC's actions fail. View "El Paso Electric Co. v. FERC" on Justia Law
Residential Util. Consumer Office v. Arizona Corp. Comm’n
Arizona Water Company (AWC), a utility company, sought a rate increase and proposed a step-increase mechanism that would allow the Arizona Corporation Commission to adjust rates between full rate cases. The rate increase mechanism, called the system improvements benefit (SIB), would allow AWC to petition for a rate increase between rate cases to help AWC recoup the cost of newly-completed infrastructure projects. The Commission approved the SIB mechanism with some modifications. The court of appeals vacated the Commission’s approval of the SIB mechanism, concluding that the SIB mechanism did not comply with the state Constitution’s mandate that “the Commission determine a public service corporation’s fair value when setting rates[.]” The Supreme Court vacated the court of appeals’ opinion and affirmed the Commission’s orders approving the SIB mechanism, holding that the SIB mechanism complied with the Constitution’s mandate that the Commission determine the fair value of a utility’s property when setting rates. View "Residential Util. Consumer Office v. Arizona Corp. Comm’n" on Justia Law
Kansas City S. Ry. v. Sny Island Levee Drainage Dist
Pike County's Sny Island Levee Drainage District was organized in 1880 to protect from Mississippi River flooding and runoff. The Kansas City Southern and the Norfolk Southern operate main line railways over the District's flood plain. Illinois law permits the District to assess properties within its territory in order to maintain the levees. A new method, adopted in 2009, purported to calculate assessments based on the benefits the District conferred on each property, rather than based on acreage. After the Seventh Circuit enjoined use of the methodology, the District discontinued collecting annual assessments and implemented a one-time additional assessment, 70 ILCS 605/5. The District filed an assessment roll based on new benefit calculations, identifying the tax on KC as $91,084.59 and on Norfolk as $102,976.18, if paid in one installment..The Railroads again filed suit, alleging that the District used a formula that discriminated against them in violation of the Railroad Revitalization and Regulatory Reform Act, 49 U.S.C. 11501. The Seventh Circuit affirmed judgment in favor of the District. The court rejected an argument that the comparison class against which their assessment should be measured is all other District properties, instead of the narrower class of commercial and industrial properties used by the district court. There was no clear error in the court’s assessment of a “battle of the experts.” View "Kansas City S. Ry. v. Sny Island Levee Drainage Dist" on Justia Law
Ellis-Hall v. Pub. Serv. Comm’n
Rocky Mountain Power is required by governing regulations to provide “indicative pricing” to a producer seeking to pursue a power purchase agreement. In 2012, Ellis-Hall Consultants, which is involved in the development of wind power projects and sought to sell power to PacifiCorp through its Rocky Mountain Power division, received an indicative pricing proposal. Rocky Mountain Power later rescinded that proposal and refused to proceed with negotiations on a power purchase agreement under its earlier indicative pricing because the Utah Public Service Commission had since adopted new pricing methodology. The Commission concluded that Ellis-Hall was not entitled to continue to rely on the methodology used in Rocky Mountain Power’s indicative pricing proposal. The Supreme Court reversed, holding that Ellis-Hall was entitled to proceed in reliance on the methodology set forth in the indicative pricing proposal it received from Rocky Mountain Power. View "Ellis-Hall v. Pub. Serv. Comm’n" on Justia Law