Justia Utilities Law Opinion Summaries

Articles Posted in U.S. Court of Appeals for the District of Columbia Circuit
by
Several electricity generators challenged a change in how they are compensated for producing reactive power, a component of electricity necessary for grid stability but not directly consumed by end users. For many years, the Midcontinent Independent System Operator (MISO) provided generators with cost-based compensation for reactive power, in addition to market-based payments for real power. In 2022, MISO amended its tariff to eliminate separate compensation for reactive power, meaning neither transmission owners nor independent generators would receive payment for producing it within a standard range. This change was approved by the Federal Energy Regulatory Commission (FERC) and given immediate effect, despite objections from generators who argued they had made investments and entered contracts in reliance on the prior compensation structure.FERC approved MISO’s tariff amendment and denied requests for rehearing, concluding that the comparability standard justified the change and that generators’ reliance interests were either unsupported or outweighed by other considerations. FERC reasoned that generators should not have expected compensation for reactive power to continue indefinitely, especially since prior orders had made such compensation contingent on similar treatment for transmission owners. Generators petitioned the United States Court of Appeals for the District of Columbia Circuit for review, arguing that FERC failed to adequately consider their short-term financial reliance on the previous compensation scheme.The United States Court of Appeals for the District of Columbia Circuit held that FERC acted arbitrarily and capriciously by failing to adequately consider the generators’ short-term reliance interests before allowing the tariff change to take immediate effect. The court did not address the substantive validity of the tariff amendment itself but found that FERC’s explanation was insufficient regarding the abrupt elimination of compensation. The court granted the petitions for review, set aside FERC’s orders, and remanded the matter for further proceedings. View "Capital Power Corp. v. Federal Energy Regulatory Commission" on Justia Law

by
Two electric utility companies merged in 1998, with federal approval conditioned on their participation in a regional grid operator to prevent customers from paying multiple, overlapping transmission fees (“pancaked” rates). Several years later, the merged company was allowed to leave the grid operator, but only if it continued to protect certain customers from redundant fees through a special rate schedule. In 2019, the company sought to end this obligation, arguing that continued protection was no longer necessary. The Federal Energy Regulatory Commission (FERC) granted this request, but the United States Court of Appeals for the District of Columbia Circuit vacated that order, finding FERC had failed to consider the impact on customer rates.On remand, FERC issued a new order denying the company’s request to end the fee protection, concluding that removing the protection would adversely affect rates for certain customers and that the benefits of removal did not outweigh these harms. FERC also denied rehearing, maintaining that the company had not shown sufficient alternative protections for affected customers. The company then petitioned the United States Court of Appeals for the District of Columbia Circuit for review, arguing that FERC’s orders were arbitrary, capricious, and inconsistent with law and precedent.The United States Court of Appeals for the District of Columbia Circuit held that FERC did not violate its statutory mandate or precedent in its general approach. However, the court found that FERC failed to adequately consider whether alternative customer protections, such as transition agreements, could mitigate the adverse rate impacts. The court therefore granted the petitions for review, vacated FERC’s orders, and remanded the matter for further consideration of whether such protections would suffice to offset the adverse effects on rates. View "Louisville Gas and Electric Company v. Federal Energy Regulatory Commission" on Justia Law

by
Petitioners, who own New York’s electric-transmission grid, sought to finance upgrades required when new power sources connect to the grid. This would allow them to raise rates and earn a return on these investments. However, the Federal Energy Regulatory Commission (FERC) denied their requests to change the rules prohibiting owner upgrade funding.The transmission owners filed two petitions with FERC on April 9, 2021, under Sections 205 and 206 of the Federal Power Act, requesting amendments to the Open Access Transmission Tariff (OATT) to allow them to fund interconnection upgrades. On September 3, 2021, FERC rejected the Section 205 filing, stating that the owners’ agreement with the New York Independent System Operator (NYISO) limited their Section 205 rights. FERC also dismissed the Section 206 complaint, concluding that the owners failed to demonstrate that the existing funding mechanism was unjust, unreasonable, unduly discriminatory, or preferential. The owners’ requests for rehearing were deemed denied by operation of law on November 4, 2021, and FERC issued a new order on March 24, 2022, modifying its original orders.The United States Court of Appeals for the District of Columbia Circuit reviewed the case and upheld FERC’s decisions. The court found that FERC acted reasonably in dismissing the Section 205 filing, as the owners had relinquished their rights to file for changes to the OATT without NYISO’s approval. The court also agreed with FERC’s dismissal of the Section 206 complaint, noting that the owners failed to provide sufficient evidence that the current rates were unjust or unreasonable. The court concluded that FERC’s orders were not arbitrary or capricious and denied the owners’ petitions for review. View "Central Hudson Gas & Electric Corporation v. FERC" on Justia Law

by
Section 309 of the Federal Power Act (FPA), 16 U.S.C. 825h, vests the Commission with broad remedial authority, including the authority to grant recoupment when it is justified; Section 201(f) does not limit the authority of the Commission to grant relief under Section 309 with respect to matters that are beyond the strictures of Sections 201(f) and 205; and an order of recoupment, as distinguished from an order to refund under Section 205, is beyond the strictures of Sections 201(f) and 205. In this case, Chehalis sought relief from the Commission by filing a Motion for an Order Requiring Recoupment of Payments, but the Commission concluded that it could not order recoupment because the Commission's refund authority does not extend to exempt public utilities such as the Intervenor Bonneville. The DC Circuit held that the Commission erred when it held that it lacked the authority to grant the Order Requiring Recoupment where the Commission clearly had jurisdiction over the subject of this dispute and the Commission retained the authority to order Bonneville to return the funds when the agency acknowledged that its initial order was mistaken. The court granted in part and denied in part Chehalis's petitions for review, and remanded for further proceedings. View "TNA Merchant Projects v. FERC" on Justia Law

by
Section 210 of the Public Utility Regulatory Policies Act of 1978 (PURPA), 16 U.S.C. 824a-3, seeks to reduce reliance on fossil fuels by increasing the number of energy-efficient cogeneration and small power-production facilities. Oregon implements its PURPA responsibilities largely through its Public Utility Commission (OPUC), which has directed utilities subject to its jurisdiction to draft off-the-shelf, standard-form power-purchase agreements that OPUC then reviews for compliance with PURPA. OPUC has approved two standard-form power-purchase agreements submitted by petitioner Portland General Electric. Petitioner PáTu Wind Farm, a six-turbine, nine-megawatt generator in rural Oregon, is classified under PURPA as a small power producer. This appeal stems from the parties' dispute over the nature of Portland General's purchase obligation. The Commission ruled that under PURPA, Portland General must purchase all of PáTu’s power, though it rejected PáTu’s insistence that Portland General do so by utilizing a technology known as dynamic scheduling. The court concluded that PáTu’s petition dealing exclusively with Portland's refusal to utilize dynamic scheduling is without merit. Accordingly, the court denied PáTu’s petition. The court dismissed Portland's petition challenging the Commission's ruling that it must purchase all of PáTu’s power for lack of jurisdiction because FERC's orders were advisory. View "Portland General Electric Comp v. FERC" on Justia Law

by
Petitioners challenged the Commissions' determinations following compliance filings by the regional transmission organization for New England's electric grid. The court concluded that the Transmission Owners have standing to bring their challenges, but concluded that the Commission's orders were not inconsistent with its past decisions; the Commission did not apply the wrong legal standard for measuring whether the Mobile-Sierra presumption had been overcome; and the Commission's determination was in accord with the evidence before it. In regard to State Petitioner's challenges, the court concluded that, in light of the clarifications made by the Commission, there is no inconsistency with Order No. 1000. The court also concluded that the Commission did not exceed its bounds of authority under the Federal Power Act (FPA), 16 U.S.C. 824(a). Accordingly, the court denied the petitions for review. View "Emera Maine v. FERC" on Justia Law

by
Transmissions Owners provide transmission services for customers in New England. Consumers, Massachusetts and various consumer-side stakeholders, filed suit under section 206 of the Federal Power Act (FPA), 16 U.S.C. 824e(a), alleging that Transmission Owners' base return on equity (ROE) had become unjust and unreasonable. At issue are FERC's orders in the section 206 proceeding. Both Transmission Owners and Customers filed petitions for review challenging whether FERC satisfied the statutory requirements under section 206 in setting a new ROE. The court explained that, to satisfy its dual burden under section 206, FERC was required to do more than show that its single ROE analysis generated a new just and reasonable ROE and conclusively declare that, consequently, the existing ROE was per se unjust and unreasonable. Therefore, the court concluded that, because FERC's single ROE analysis failed to include an actual finding as to the lawfulness of Transmission Owners' existing base ROE, FERC acted arbitrarily and outside of its statutory authority in setting a new base ROE for Transmission Owners. The court also concluded that FERC failed to provide any reasoned basis for selecting 10.57 percent as the new base ROE. Accordingly, the court granted the petitions for review, vacated FERC's orders, and remanded for further proceedings. View "Maine v. FERC" on Justia Law

by
Section 205 of the Federal Power Act (FPA), 16 U.S.C. 824d(a), mandates that all rates and charges demanded, or received by any public utility for the transmission or sale of electric energy subject to the jurisdiction of the Commission shall be just and reasonable. Xcel petitioned for review of three of the Commission's orders denying a retroactive refund for unlawful rates. As a preliminary matter, the court concluded that, to the extent the Commission denied Xcel relief because it lacks authority to order refunds from Tri-County, a non-jurisdictional entity, this was not responsive to Xcel’s request. On the merits, the court concluded that the Commission’s reliance on section 2.4(a) of its regulations and related cases to deny Xcel retroactive relief is misplaced. Because the Commission’s reliance on section 2.4(a) of its regulations as applied in its precedent is inapposite, and its position that its section 205 error of law is irremediable beyond prospective relief under section 206 appears irreconcilable with the authority Congress granted it in section 309 to remedy its errors, the court granted the petition in part and remanded the case to the Commission for appropriate action. View "Xcel Energy Servs. Inc. v. FERC" on Justia Law

by
On September 16, 2013, the Commission issued an Order Conditionally Accepting Tariff Revisions filed by ISO New England. In the same order, the Commission rejected the tariff proposal to allocate costs to transmission owners as inconsistent with cost-causation principles and directed ISO New England to submit a compliance filing that would allocate the costs of the Program to Real-Time Load Obligation. On April 8, 2014, FERC issued orders denying requests for rehearing of the Orders issued in Docket ER13-1851 and Docket ER13-2266. TransCanada and the Retail Energy Supply Association filed petitions for review challenging the Orders issued by FERC approving the Winter 2013-14 Reliability Program. The court declined to assess FERC’s conditional approval of the Program in Docket ER13-1851 because FERC made it clear that its decision was only tentative. The court concluded that the Commission’s decision regarding the allocation of the costs of the Program to Load-Serving Entities was a final action in Docket ER13-1851 and is ripe for review; the court found no merit in petitioners' challenges to the cost-allocation decision; and therefore, the court denied the petitions for review of the cost-allocation decision in Docket ER13-1851. The court granted in part the petition for review of Docket ER13-2266 because FERC could not properly assess whether the Program’s rates were just and reasonable. View "TransCanada Power Marketing v. FERC" on Justia Law

by
Western Minnesota and intervenors petitioned for review of FERC's award of a permit for a hydroelectric project in Polk County, Iowa. The Commission concluded that the municipal preference under Section 7(a) of the Federal Power Act (FPA), 16 U.S.C. 800(a), applies only to municipalities “located in the[] vicinity” of the water resources to be developed. Petitioners claimed that the Commission’s geographic proximity test is an impermissible interpretation of the plain text of the statute. The court agreed that Congress has spoken directly to the question in defining “municipality” in Section 3(7) of the FPA. Accordingly, the court granted the petition for review, vacated the permit order and rehearing order, and remanded for further proceedings. View "Western Minnesota Municipal v. FERC" on Justia Law