Justia Utilities Law Opinion Summaries

Articles Posted in Utilities Law
by
In the case before the United States Court of Appeals for the Sixth Circuit, Brandenburg Telephone Company and Sprint Communications were in disagreement over the interest rate on an award that Sprint Communications conceded it owed to Brandenburg Telephone Company. The $2.2 million award was for unpaid fees that Sprint Communications owed for connecting local telephone calls. The dispute centered on Brandenburg's filed utility tariff which set the interest rate. Sprint argued that the tariff set the rate at 8%, and thus owed $4.3 million in interest, while Brandenburg claimed the tariff imposed a rate of 10.66%, which would result in $7.1 million in interest. The district court ruled in favor of Sprint, and the appeals court affirmed this decision.The court reasoned that the 8% rate set by the Kentucky usury statute was applicable. The court noted that while Brandenburg's tariff offered two alternatives for late payment penalty: (1) the highest interest rate (in decimal value) which may be levied by law for commercial transactions, or (2) a rate of .000292 per day (which works out to an annualized rate of 10.66%); the court interpreted the phrase "levied by law for commercial transactions" to refer to the default rate that Kentucky permits to be collected by law, which is 8%.The court rejected Brandenburg's argument that the 10.66% rate was applicable because the tariff could be viewed as an agreement between the parties and Kentucky law allows for parties to agree on higher interest rates. The court pointed out that tariffs are not freely negotiated contracts, but represent the judgment of regulators about what rates and conditions will prove reasonable and uniform for utility customers. Once regulators approve a tariff, the filed-rate doctrine prevents utilities and their customers from contracting around its terms. In this context, the court determined that the tariff's reference to the maximum rate levied by the General Assembly for general commercial transactions aligned with the filed-rate doctrine, and thus, the 8% default rule of interest applied. View "Brandenburg Telephone Co. v. Sprint Comm'ns Co." on Justia Law

by
The United States Court of Appeals for the District of Columbia Circuit examined a case involving the City of Lincoln, also known as Lincoln Electric, a public utility providing electricity to the Lincoln, Nebraska area. Lincoln Electric had invested in the Laramie River Station facilities (LRS) in eastern Wyoming as a source of generation and transmission, despite only serving customers in the Lincoln area.When Lincoln Electric joined the Southwest Power Pool (SPP) in 2009, it transferred control of all its facilities in the Lincoln area to SPP, but retained control of its LRS interest. In 2021, the SPP proposed that Lincoln Electric recover its LRS costs from Zone 19 customers, where LRS is physically located. Other co-owners of the LRS facilities recover their costs from Zone 19 customers.The Federal Energy Regulatory Commission (FERC) rejected the SPP proposal as unjust and unreasonable because Zone 19 customers neither caused Lincoln Electric's LRS investment nor benefited from it, thus violating the cost-causation principle. Lincoln Electric petitioned for review of the relevant FERC orders and the SPP intervened on Lincoln Electric's behalf.The court upheld FERC's decision, ruling that Lincoln Electric failed to demonstrate that the proposed rates were just and reasonable. The court concluded that cost allocation must reflect the costs actually caused by the customer who must pay them. In this case, Lincoln Electric's investment in the LRS was for the benefit of its own Zone 16 customers, not Zone 19 customers. As such, the court found that allocating Lincoln Electric's LRS costs to Zone 19 would violate the cost-causation principle. The petition for review was denied. View "City of Lincoln v. FERC" on Justia Law

by
In the case before the Maine Supreme Judicial Court, the Office of the Public Advocate (the appellant) contested a decision by the Public Utilities Commission (PUC) that approved an amended special rate contract between Bangor Natural Gas Company and Bucksport Generation LLC. The appellant argued that the PUC applied the wrong standard in reviewing the contract, which led to unjust or unreasonable rates and undue or unreasonable preference for Bucksport Generation over other Bangor Gas customers. The appellant also argued that the PUC's order should be vacated because it relied on evidence not included in the record.The court disagreed with the appellant's first argument and found the second argument waived, thereby affirming the PUC's order. The court held that the PUC was within its discretion to apply different standards of review for special rate contracts depending on the type of utility service at issue. Given the competitive nature of the natural gas market in Maine, the court deemed the PUC's standard reasonable.Regarding the rates, the court found that the PUC’s approval of the special rate contract did not result in unjust, unreasonable, or discriminatory rates for other Bangor Gas customers. The court noted that incentivizing continued financial contributions from Bucksport Generation to Bangor Gas’s fixed costs was justifiable.Finally, the court ruled that the appellant's argument about the PUC's failure to create an evidentiary record was waived due to the appellant's failure to raise the issue at the PUC level. However, the court acknowledged the appellant's point and advised the PUC to clarify its regulations regarding what materials constitute the evidentiary record in proceedings where an evidentiary hearing is not held. View "Office of the Public Advocate v. Public Utilities Commission" on Justia Law

by
The Court of Appeal of the State of California was asked to review a decision by the Public Utilities Commission (PUC) that adopted a new tariff (pricing structure) for utility customers who generate their own power from renewable sources, such as solar panels. This new tariff significantly reduces the price utilities pay for customer-generated power. The petitioners, a group of environmental organizations, argued that the new tariff fails to comply with various requirements imposed by state law, including that it doesn't take into account the societal benefits of customer-generated power, it favors utility customers who don't own renewable systems, it doesn't promote sustainable growth of renewable energy, and it doesn't promote the growth of renewable systems among customers in disadvantaged communities. The court upheld the PUC's decision.The court found that the PUC's decision to base the price paid for exported power on the marginal cost of energy to the utilities served the goal of equity among customers. The court also determined that the PUC's decision complied with the statutory mandate to ensure that the tariff does not grant unwarranted benefits or impose unwarranted costs on any particular group of ratepayers. Lastly, the court found the PUC's efforts to stimulate the adoption of renewable systems in disadvantaged communities sufficient to meet its statutory obligation. View "Center for Biological Diversity v. Public Utilities Com." on Justia Law

by
In a dispute involving a power grid operator, PJM Interconnection, L.L.C., and the Federal Energy Regulatory Commission (FERC), the United States Court of Appeals for the Sixth Circuit ruled that the Chairman of FERC exceeded his authority by seeking a remand of a ratemaking challenge without the support of other Commission members.The case originated when PJM filed a request to modify its existing rates for electricity reserves, arguing that the existing rates were unjust and unreasonable. Initially, FERC agreed and approved the new rates. However, after a change in FERC's composition and a unilateral decision by the Chairman to request a voluntary remand from the D.C. Circuit for reconsideration, FERC reversed its decision and found PJM's evidence insufficient.The Sixth Circuit's ruling focused on the procedural irregularity, specifically the Chairman's unilateral decision to seek a remand, which it deemed exceeded his administrative authority. The court stated that a quorum majority must decide the Commission’s policy and dealings with the outside world, and the Chairman acting alone does not meet this requirement. As such, the court vacated the part of FERC's rehearing order that claimed the Chairman had this unilateral authority and remanded the matter back to FERC to address this issue.The court did not address the substantive issue of whether FERC's reversal on the ratemaking decisions was arbitrary and capricious. It noted that any interested party may renew a petition to challenge that decision after FERC resolves the procedural issue. View "PJM Power Providers Grp. v. FERC" on Justia Law

by
In a case involving the Federal Energy Regulatory Commission (FERC) and the Electric Power Supply Association and PJM Power Providers Group (collectively, PJM), the United States Court of Appeals for the Sixth Circuit had to address two questions. The first was whether the Chairman of FERC exceeded his authority when he moved for a remand of a ratemaking challenge without the support of any other members of the Commission, and the second was whether FERC's underlying ratemaking decisions were arbitrary and capricious.The case arose from PJM's request to FERC to raise the reserve price cap for electricity from $850 to $2,000 per megawatt hour and to replace the flat $300 per megawatt hour cap after Step 1 with a downward sloping price schedule. Initially, FERC agreed with PJM that the existing price cap and stepwise demand curve were unjust and unreasonable. However, after a change in the composition of the FERC, the Commission sought a voluntary remand from the D.C. Circuit to reconsider its prior decisions. The D.C. Circuit granted the unopposed motion for remand. On remand, the Commission reversed its previous decision and found PJM's evidence insufficient to show that the price caps for reserves and stepwise demand curve were unjust and unreasonable.PJM and others sought rehearing before the Commission, citing a procedural irregularity - the Chairman had directed FERC's Solicitor to seek remand without first informing the other Commissioners - and challenging the substance of the agency’s shift in views. The Commission rejected the request for rehearing but issued a modified order, reaching the same result, and reasoning that Chairman Glick had the unilateral authority to make the remand motion.The Court of Appeals for the Sixth Circuit held that the Chairman of FERC exceeded his legal authority when he requested a remand in the name of the Commission on his own. The court vacated part of the Commission’s order claiming the Chairman had this unilateral authority and remanded the case back to the Commission to decide what, if anything, it could or would have done differently in response to this legal mistake. The court did not rule on whether FERC's underlying ratemaking decisions were arbitrary and capricious, leaving it to the Commission to first resolve the legal mistake. View "Electric Power Supply Ass'n v. FERC" on Justia Law

by
This case involves a dispute over a tariff adopted by the Public Utilities Commission (Commission) of the State of California that affects the compensation utilities provide to customers for excess electricity generated by renewable energy systems. The tariff, known as the net energy metering (NEM) tariff, previously required utilities to purchase excess electricity from renewable systems at the same price customers pay for electricity. However, utilities complained that this overcompensated the owners of renewable systems and raised the cost of electricity for customers without renewable systems. In response, the California Legislature enacted a law requiring the Commission to adopt a successor tariff that promotes the continued sustainable growth of renewable power generation while balancing costs and benefits to all customers.Several environmental groups challenged the Commission's newly adopted successor tariff, asserting that it did not comply with various statutory requirements. The Court of Appeal of the State of California First Appellate District upheld the Commission's tariff. The court found that the Commission's successor tariff adequately served the various objectives of the law and was based on a reasonable interpretation of its statutory mandate. The court also found that the Commission's decision to value exported energy from renewable systems based on the marginal cost of energy to the utilities was a reasonable approach to fulfilling the law's requirement to balance the equities among all customers. The court rejected the plaintiffs' arguments that the Commission had failed to properly account for the costs and benefits of renewable energy, and that it had improperly favored the interests of utility customers who do not own renewable systems. The court also found that the Commission had properly fulfilled the law's requirement to include specific alternatives designed for growth among residential customers in disadvantaged communities. The court affirmed the decision of the Commission. View "Center for Biological Diversity v. Public Utilities Com." on Justia Law

by
In this dispute, two renewable-energy generating companies, Tyngsboro Sports II Solar, LLC and 201 Oak Pembroke Solar LLC, appealed to the United States Court of Appeals for the First Circuit after their class-action lawsuit was dismissed by the District Court for the District of Massachusetts due to lack of subject-matter jurisdiction. The plaintiffs had a longstanding disagreement with defendants, utility companies National Grid USA Service Company, Inc. and Massachusetts Electric Company, over certain tax-related fees charged to them. The plaintiffs sought redress in federal court after unsuccessful petitions to state authorities.The plaintiffs argued that the district court had jurisdiction due to the case's connection to federal tax law, however, the appellate court disagreed, stating that the plaintiffs' complaint did not bring any claim that arose under federal law. The plaintiffs had brought forth four claims against National Grid, including a request for declaratory relief, a state-law claim for a breach of the covenant of good faith and fair dealing, a state-law claim for restitution and unjust enrichment, and a state-law claim for violating a statutory requirement that public utilities assess only just and reasonable charges.The appellate court affirmed the district court's dismissal of the case, finding that the plaintiffs could not establish federal-question jurisdiction simply by asserting a state-law claim to which there was a federal defense. The court noted that the state-law claims did not necessarily raise a federal issue, and to the extent that one did, the issue was not substantial. As such, the court concluded that the district court lacked jurisdiction over the claims. View "Tyngsboro Sports II Solar, LLC v. National Grid USA Service Co., Inc." on Justia Law

by
The Supreme Court held, in response to a request by the United States Court of Appeals for the Ninth Circuit, that Cal. Publ. Util. Code 1759 bars a lawsuit that seeks damages resulting from public safety power shutoffs (PSPS) events where the suit alleges that a utility's negligence in maintaining its grid necessitated shutoffs but does not allege that the shutoffs were unnecessary or violated the regulations of the California Public Utilities Commission (PUC).To reduce the risk that its utility infrastructure would ignite a wildfire during extreme weather conditions Pacific Gas and Electric Company (PG&E) conducted a series of emergency power shutoffs that Plaintiff alleged were necessitated by PG&E's negligence in maintaining its power grid. Plaintiff filed a class action complaint against PG&E requesting class damages of $2.5 billion. At issue before the Supreme Court was whether section 1759 barred this lawsuit. The Supreme Court answered the question in the positive, holding that allowing suit under the circumstances here would interfere with the PUC's comprehensive regulatory and supervisory authority over PSPS. View "Gantner v. PG&E Corp." on Justia Law

by
Petitioner Liberty Utilities (EnergyNorth Natural Gas) Corp., d/b/a Liberty (Liberty), appealed a New Hampshire Public Utilities Commission order denying Liberty’s request to recover development costs related to a proposed natural gas pipeline and tank system, the Granite Bridge project. This case arose from an unrealized construction project. Liberty relied solely on Tennessee Gas Pipeline Co., LLC (Tennessee Gas Pipeline) for its gas supply in southern and central New Hampshire. Liberty executives testified that Liberty sought more supply from Tennessee Gas Pipeline because Liberty was facing increased demand. Liberty and Tennessee Gas Pipeline agreed to an arrangement whereby Liberty would receive additional gas from a second pipeline, but Tennessee Gas Pipeline cancelled that arrangement. In response, Liberty began to explore other options, and eventually decided to construct its own pipeline and tank system, the Granite Bridge project. Liberty estimated that $7.5 million of that amount consisted of engineering, environmental, consulting, internal labor, commission related costs, and land costs. Despite those costs, according to Liberty, it would have been years before Liberty broke ground on Granite Bridge. Later, Tennessee Gas Pipeline offered Liberty more space on its pipeline at a cheaper rate than the projected cost of Granite Bridge. Liberty accepted that offer, and then cancelled the Granite Bridge project. The New Hampshire Supreme Court concluded Liberty could not recover its costs when it cancelled the project and consumers derived no benefit. The Commission's order was thus affirmed. View "Appeal of Liberty Utilities (EnergyNorth Natural Gas) Corp., D/B/A Liberty" on Justia Law