Justia Utilities Law Opinion Summaries

Articles Posted in Utilities Law
by
This appeal concerns the Texas PUC's interpretation and implementation of a federal statutory and regulatory scheme governing the purchase of energy between public utilities and certain energy production facilities known as Qualifying Facilities. Exelon, qualifying wind generation facilities, challenged a state rule and order which prohibited it from forming Legally Enforceable Obligations when selling power. The court vacated the portion of the judgment regarding Exelon's challenge to the PUC's order and directed the district court to dismiss for want of subject matter jurisdiction. The court reversed as to the remaining challenges to the rule and remanded because PUC acted within its discretion and properly implemented the federal regulation at issue. View "Exelon Wind 1, L.L.C., et al. v. Nelson, et al." on Justia Law

by
After electrical outages arising from Tropical Storm Irene on August 28, 2011 and a snowstorm two months later, the Department of Public Utilities entered orders against three utility companies - National Grid, NSTAR Electric Company (NSTAR), and Western Massachusetts Electric Company (WMEC) - that imposed monetary penalties for the utilities’ failure to restore service to their customers “in a safe and reasonably prompt manner.” The Supreme Judicial Court affirmed in part and reversed in part, holding (1) the Department applied the appropriate reasonableness standard in finding that the utilities violated their duty to restore service in a safe and reasonably prompt manner; (2) the Department’s findings regarding National Grid and WMEC were supported by substantial evidence, but its finding that NSTAR failed timely to respond to priority two and three wires-down calls was not supported by substantial evidence; and (3) with two exceptions, the Department made the necessary findings and did not abuse its discretion in its imposition of monetary penalties. Remanded. View "Mass. Elec. Co. v. Dep’t of Pub. Utils." on Justia Law

by
This appeal stemmed from the Public Utilities Commission’s first annual review of the fuel-adjustment clause (FAC) mechanism that was part of the first electric security plan (ESP) for two American Electric Power operating companies, Columbus Southern Power and Ohio Power Company. The FAC allowed the companies to recover fuel costs for providing generation service as those costs were incurred without being required to file a new rate case. An auditor found that the companies had underrecovered fuel costs through the FAC in 2009. After review, the Commission concluded (1) all of the proceeds that AEP had received from a 2008 contract settlement agreement with a coal supplier should be offset against Ohio Power’s FAC underrecovery; and (2) only the share of the settlement proceeds allocable to Ohio retail customers must be credited. Ohio Power appealed, and Industrial Energy Users-Ohio (IEU) cross-appealed. The Supreme Court affirmed the Commission’s orders, holding that Ohio Power and IEU did not carry their burden of showing reversible error in the Commission’s orders. View "In re Fuel Adjustment Clauses for Columbus S. Power Co. & Ohio Power Co." on Justia Law

by
Florida Power & Light (FPL) filed an application for a rate base increase. Three intervenors to the proceedings and FPL reached a negotiated settlement agreement. After evidentiary hearings pertaining exclusively to the settlement agreement, the Florida Public Service Commission (Commission) approved the settlement agreement, finding that it established fair, just, and reasonable rates and that it was in the public interest. Citizens of the State of Florida (Citizens) appealed the decision of the Commission. The Supreme Court affirmed, holding (1) the Commission did not violate the essential requirements of the law or commit a material error in procedure by approving the negotiated settlement agreement over Citizens’ objection; (2) the procedures followed by the Commission did not violate Citizens’ due process rights; and (3) the Commission’s findings and conclusions were support by competent, substantial evidence and were not clearly erroneous. View "Citizens of the State of Fla. v. Pub. Serv. Comm’n" on Justia Law

by
Plaintiffs filed a putative class action against defendants alleging that defendants violated the Fair Debt Collection Practices Act (FDCPA), 15 U.S.C. 1692 et seq., and New York statutory and common law. Plaintiffs alleged that defendants obtained unauthorized attorneys' fees and costs in connection with actions to foreclose liens on plaintiffs' properties arising out of unpaid municipal property taxes and water and sewer charges. The court held that liens for mandatory water and sewer charges imposed by New York City as an incident to property ownership, which are treated as akin to property tax liens, are not subject to the FDCPA because they do not involve a "debt" as that term is defined in the statute. The court also held that the district court properly declined to exercise supplemental jurisdiction over the state law claims. Accordingly, the court affirmed the judgment of the district court. View "Boyd v. J.E. Robert Co., Inc." on Justia Law

by
The Federal Power Act, 16 U.S.C. 824d(c), requires regulated utilities to file with the Commission, as a matter of open and accessible public record, any rates and charges they intend to impose for sales of electrical energy that are subject to the Commission's jurisdiction. Consequently, utilities are forbidden to charge any rate other than the one on file with the Commission, a prohibition known as the "filed rate doctrine." At issue on appeal was, when a utility filed more than one rate with the Commission during the time it was negotiating an agreement with a prospective customer, which of the two filed rates governs: the rate at the time negotiations commenced or the rate at the time the agreement was completed? The Commission is of the view that it can pick and choose which rate applies on a case-by-case basis. Because the Commission has provided no reasoned explanation for how its decision comports with statutory direction, prior agency practice, or the purposes of the filed rate doctrine, the court vacated the Commission's orders in part and remanded. View "West Deptford Energy, LLC v. FERC" on Justia Law

by
The Corporation, asserting its power under section 215(e) of the Federal Power Act, 16U.S.C. 824o, assessed a monetary fine against Southwestern, a federal government entity that markets hydroelectric power. The Commission upheld the penalty. The court held that section 215(b)(1) generally subjects federal government entities to the Commission's jurisdiction to enforce compliance. But to authorize a monetary award against the federal government, the statute must do more than generally bring the government within the Commission's enforcement jurisdiction - it must unequivocally subject the government to monetary liability. Neither section 215(b) nor section 215(e), nor the two consolidated in combination, speaks with the requisite clarity to waive the federal government's sovereign immunity from monetary penalties. Therefore, the court vacated the Commission's order. View "Southwestern Power Admin., et al. v. FERC" on Justia Law

by
Duke Energy Progress filed an application with the North Carolina Utilities Commission requesting authority to increase its retail electric service rates and that rates be established using a return on equity (ROE) of 11.25 percent. The Commission entered an order approving an ROE of 10.2 percent. The Attorney General, who had intervened in the proceedings, appealed the Commission’s order. The Supreme Court affirmed, holding that the Commission made sufficient findings of fact regarding the impact of changing economic conditions upon customers and that these findings were supported by competent, material, and substantial evidence in view of the entire record. View "State ex rel. Utils. Comm'n v. Cooper" on Justia Law

by
Montana-Dakota Utilities Company (MDU) was ordered by the Wyoming Public Service Commission to make refunds of the amounts MDU had overcharged its customers because of improper calculations and adjustments to its commodity balancing account. MDU filed a petition for review, challenging the legal authority of the Commission to order refunds. The district court affirmed the Commission’s decision. The Supreme Court affirmed, holding (1) the rule against retroactive ratemaking did not preclude the Commission from ordering the refund; (2) the Commission’s refund order did not violate the file rate doctrine; (3) the Commission was not subject to a statute of limitations in this case; (4) MDU failed to show that the Commission was equitably estopped from ordering a refund; and (5) the Commission’s action was not arbitrary, capricious, an abuse of discretion, or unlawful. View "Montana-Dakota Utils., Co. v. Wyo. Pub. Serv. Comm’n" on Justia Law

by
This case involves challenges to the most recent forms of electric transmission planning and cost allocation adopted by the Commission under the Federal Power Act, 16 U.S.C. 791 et seq. In Order No. 1000, as reaffirmed and clarified in Order Nos. 1000-A and 1000-B (together, the Final Rule), the Commission required each transmission owning and operating public utility to participate in regional transmission planning that satisfies the specific planning principles designed to prevent undue discrimination and preference in transmission service, and that produces a regional transmission plan. The court held that the Commission had authority under Section 206 of the Act to require transmission providers to provide in a regional planning process; there was substantial evidence of a theoretical threat to support adoption of the reforms in the Final Rule; the Commission had authority under Section 206 to require removal of federal rights of first refusal provisions upon determining they were unjust and unreasonable practices affecting rates, and that determination was supported by substantial evidence and was not arbitrary and capricious; the Mobile-Sierra objection to the removal is not ripe; the Commission had authority under Section 206 to require the ex ante allocation of the costs of new transmission facilities among beneficiaries, and that its decision regarding scope was not arbitrary or capricious; the Commission reasonably determined that regional planning must include consideration of transmission needs driven by public policy requirements; and the Commission reasonably relied upon the reciprocity condition to encourage non-public utility transmission providers to participate in a regional planning process. Accordingly, the court denied the petitions for review of the Final Rule. View "South Carolina Public Service v. FERC" on Justia Law