Justia Utilities Law Opinion Summaries
Articles Posted in Utilities Law
Transource Pennsylvania LLC v. DeFrank
A company sought approval to construct electricity transmission lines in Pennsylvania as part of a larger project selected through a federally supervised regional planning process. The project was designed to alleviate regional congestion on the electricity grid, which would lower wholesale electricity costs in certain states but increase costs for some Pennsylvania consumers. The regional transmission organization (PJM), acting under Federal Energy Regulatory Commission (FERC) rules, selected the project using a benefit-cost methodology approved by FERC.The Pennsylvania Public Utility Commission (PUC) reviewed the company’s applications for siting and eminent domain authority. After an evidentiary hearing, an administrative law judge recommended denial, finding that the project was no longer needed due to decreased congestion and that the benefit-cost analysis used by PJM was deficient under Pennsylvania law. The PUC adopted this recommendation, denied the applications, and rescinded the company’s provisional certificate of public convenience. The company appealed to the Pennsylvania Commonwealth Court, which affirmed the PUC’s decision. The company then pursued federal constitutional claims in the United States District Court for the Middle District of Pennsylvania, reserving those issues in state court.The United States Court of Appeals for the Third Circuit reviewed the case. It held that the PUC’s order was preempted under the Supremacy Clause of the U.S. Constitution because it posed an obstacle to federal objectives established by Congress and implemented by FERC—specifically, the regional planning and congestion-reduction process. The court found that the PUC’s independent “need” determination, which second-guessed PJM’s FERC-approved methodology, impermissibly conflicted with federal law. The Third Circuit affirmed the District Court’s judgment for the company and did not reach the dormant Commerce Clause issues. View "Transource Pennsylvania LLC v. DeFrank" on Justia Law
Center for Biological Diversity, Inc. v. Public Utilities Com.
This case involves a challenge to a tariff adopted by the California Public Utilities Commission (Commission) that significantly reduced the compensation utilities pay to customers who generate electricity through rooftop solar panels and export excess energy to the grid. Petitioners, including environmental organizations, argued that the Commission’s tariff was inconsistent with Public Utilities Code section 2827.1, which requires the Commission to ensure that compensation for customer-generators reflects the costs and benefits of renewable generation and supports sustainable growth, particularly among disadvantaged communities.The First Appellate District, Division Three, of the California Court of Appeal granted a writ of review and affirmed the Commission’s decision. In doing so, the Court of Appeal applied a highly deferential standard of review derived from the California Supreme Court’s decision in Greyhound Lines, Inc. v. Public Utilities Com., asking only whether the Commission’s interpretation of the statute bore a reasonable relation to statutory purposes and language. The court concluded that the Commission’s approach satisfied this standard and declined to engage in a more searching review of the statutory interpretation.The Supreme Court of California reviewed the case to determine whether the deferential Greyhound standard remains appropriate following legislative amendments to the Public Utilities Code. The Supreme Court held that, for Commission decisions not pertaining solely to water corporations, the deferential Greyhound standard no longer applies. Instead, courts must independently review the Commission’s statutory interpretations under the standards set forth in Public Utilities Code sections 1757 and 1757.1, which parallel the review of other administrative agencies. The Supreme Court reversed the judgment of the Court of Appeal and remanded the case for further proceedings consistent with this less deferential standard. View "Center for Biological Diversity, Inc. v. Public Utilities Com." on Justia Law
Client Earth v. Washington Gas Light Company
Three public interest organizations brought suit against a utility company that provides natural gas services in the District of Columbia, alleging that the company violated the Consumer Protection Procedures Act (CPPA) by making false and misleading statements about the environmental effects of its natural gas. The organizations claimed these statements appeared in customer bills, on the company’s website, and in other public documents. They sought declaratory and injunctive relief to address the alleged unfair and deceptive trade practices.The utility company responded by filing a special motion to dismiss under the District’s Anti-SLAPP Act, followed by a motion to dismiss under Superior Court Civil Rules 12(b)(1) and 12(b)(6). The company argued that the CPPA does not create a right of action against entities regulated by the Public Service Commission (PSC), citing D.C. Code § 28-3903(c)(2)(B) and the District of Columbia Court of Appeals’ decision in Gomez v. Independence Management of Delaware, Inc., 967 A.2d 1276 (D.C. 2009). The public interest organizations countered that the statutory limitation only applied to the Department of Licensing and Consumer Protection, not to private actors like themselves, and that subsequent amendments to the CPPA had rendered Gomez obsolete. The Superior Court granted the utility’s motion to dismiss, finding that Gomez remained controlling and that the CPPA’s exemptions for PSC-regulated entities had not been altered by later amendments.On appeal, the District of Columbia Court of Appeals affirmed the Superior Court’s dismissal. The court held that, although the plain text of the CPPA does not expressly bar private suits against PSC-regulated entities, binding precedent from Gomez requires that the limitations in D.C. Code § 28-3903(c)(2) apply to private actions as well. Therefore, public interest organizations may not sue entities regulated by the PSC under the CPPA. View "Client Earth v. Washington Gas Light Company" on Justia Law
Patz v. City of San Diego
A group of single-family residential (SFR) water customers challenged the City of San Diego’s tiered water rate structure, which imposed higher rates for increased water usage, arguing that these rates exceeded the proportional cost of service attributable to their parcels as required by California Constitution article XIII D, section 6(b)(3) (enacted by Proposition 218). The City’s water system serves a large population and divides customers into several classes, but only SFR customers were subject to tiered rates; other classes paid uniform rates. The City’s rates were based on cost-of-service studies using industry-standard methodologies, including “base-extra capacity” and “peaking factors,” but the plaintiffs contended these methods did not accurately reflect the actual cost of providing water at higher usage tiers.The Superior Court of San Diego County certified the case as a class action and held a bifurcated trial. In the first phase, the court found that the City failed to demonstrate, with substantial evidence, that its tiered rates for SFR customers complied with section 6(b)(3), concluding the rates were not based on the actual cost of service at each tier but rather on usage budgets and conservation goals. The court also found the City lacked sufficient data to justify its allocation of costs to higher tiers and that the rate structure discriminated against SFR customers compared to other classes. In the second phase, the court awarded the class a refund for overcharges, offset by undercharges, and ordered the City to implement new, compliant rates.On appeal, the California Court of Appeal, Fourth Appellate District, Division Two, affirmed the trial court’s judgment with directions. The appellate court held that the City bore the burden of proving its rates did not exceed the proportional cost of service and that the applicable standard was not mere reasonableness but actual cost proportionality, subject to independent judicial review. The court found substantial evidence supported the trial court’s findings that the City’s tiered rates were not cost-based and thus violated section 6(b)(3). The court also upheld class certification and the method for calculating the refund, and directed the trial court to amend the judgment to comply with newly enacted Government Code section 53758.5, which affects the manner of refunding overcharges. View "Patz v. City of San Diego" on Justia Law
In re Application of Ohio Power Co.
One Power Company challenged two orders issued by the Public Utilities Commission of Ohio (PUCO) regarding Ohio Power Company’s fifth electric-security plan. The first issue concerned a protective agreement governing access to confidential discovery materials. One Power argued that the agreement unreasonably prevented its chief executive officer and expert witness, an employee, from accessing all discovery, which allegedly disadvantaged its ability to litigate. The second issue involved the commission’s decision to continue a nonbypassable basic-transmission-cost rider, meaning all customers—including those who purchase generation service from competitive suppliers—must pay the charge.After AEP Ohio filed its application for the fifth electric-security plan, One Power intervened and sought broader access to confidential materials. The PUCO’s attorney examiner denied One Power’s motion for a more permissive protective agreement, finding the proposed limits reasonable. One Power’s interlocutory appeal was also denied. At the evidentiary hearing, One Power renewed its objections, but the commission affirmed the examiner’s rulings and later denied rehearing. Regarding the transmission rider, the commission maintained its nonbypassable status, citing the need for further study before making major changes and noting consistency with prior practice. One Power’s rehearing application on this issue was also denied.On appeal, the Supreme Court of Ohio reviewed whether the PUCO’s orders were unlawful or unreasonable. The court held that One Power failed to demonstrate particularized harm from the protective agreement and that the commission acted within its statutory and regulatory authority in continuing the nonbypassable rider. The court found no violation of state electric policy or commission precedent. Accordingly, the Supreme Court of Ohio affirmed the PUCO’s orders. View "In re Application of Ohio Power Co." on Justia Law
Posted in:
Supreme Court of Ohio, Utilities Law
In re Application of Dayton Power & Light Co.
Dayton Power and Light Company (DP&L), operating as AES Ohio, sought approval from the Public Utilities Commission of Ohio (PUCO) regarding whether its electric security plan (ESP) resulted in significantly excessive earnings for the years 2018 and 2019. The ESP is a mechanism for setting the standard generation rate for customers who do not choose a competitive supplier. During this period, DP&L also transitioned from its third ESP (ESP III) back to its first ESP (ESP I) after the commission invalidated a similar rider in another utility’s plan, following a decision by the Supreme Court of Ohio. DP&L’s parent company, AES Corporation, made substantial capital contributions to support future investments in grid modernization.PUCO consolidated several related cases and found that DP&L’s ESP resulted in excessive earnings of $3.7 million in 2018 and $57.4 million in 2019. However, PUCO determined that DP&L could offset these excessive earnings with its commitment to future capital investments, and therefore, no refund to consumers was required. PUCO also found that DP&L’s ESP passed the required quadrennial review tests, including a prospective analysis of earnings and a comparison to market-rate offers. The Office of the Ohio Consumers’ Counsel (OCC) appealed, challenging the refusal to order refunds and the continued collection of a rate-stabilization charge. DP&L filed a protective cross-appeal, asserting alternative grounds for affirmance.The Supreme Court of Ohio reviewed the case and held that PUCO was not authorized under R.C. 4928.143(F) to allow DP&L to retain significantly excessive earnings based solely on its commitment to future investments. The court reversed PUCO’s orders and remanded the case for a new significantly excessive earnings test analysis. The court rejected OCC’s challenge to the rate-stabilization charge, finding its legality was not at issue in this appeal, and also rejected DP&L’s alternative grounds for affirmance. View "In re Application of Dayton Power & Light Co." on Justia Law
Posted in:
Supreme Court of Ohio, Utilities Law
Louisville Gas and Electric Company v. Federal Energy Regulatory Commission
Two electric utility companies merged in 1998, with federal approval conditioned on their participation in a regional grid operator to prevent customers from paying multiple, overlapping transmission fees (“pancaked” rates). Several years later, the merged company was allowed to leave the grid operator, but only if it continued to protect certain customers from redundant fees through a special rate schedule. In 2019, the company sought to end this obligation, arguing that continued protection was no longer necessary. The Federal Energy Regulatory Commission (FERC) granted this request, but the United States Court of Appeals for the District of Columbia Circuit vacated that order, finding FERC had failed to consider the impact on customer rates.On remand, FERC issued a new order denying the company’s request to end the fee protection, concluding that removing the protection would adversely affect rates for certain customers and that the benefits of removal did not outweigh these harms. FERC also denied rehearing, maintaining that the company had not shown sufficient alternative protections for affected customers. The company then petitioned the United States Court of Appeals for the District of Columbia Circuit for review, arguing that FERC’s orders were arbitrary, capricious, and inconsistent with law and precedent.The United States Court of Appeals for the District of Columbia Circuit held that FERC did not violate its statutory mandate or precedent in its general approach. However, the court found that FERC failed to adequately consider whether alternative customer protections, such as transition agreements, could mitigate the adverse rate impacts. The court therefore granted the petitions for review, vacated FERC’s orders, and remanded the matter for further consideration of whether such protections would suffice to offset the adverse effects on rates. View "Louisville Gas and Electric Company v. Federal Energy Regulatory Commission" on Justia Law
Center for Biological Diversity, Inc. v. Public Utilities Com.
This case involves a dispute over the compensation structure for utility customers who generate their own electricity, such as through rooftop solar panels, and export excess energy to the power grid. The California Legislature has required utilities to compensate these “customer-generators” since 1995, but concerns arose that the original compensation method overpaid such customers and shifted costs to those without solar systems. In 2013, the Legislature directed the Public Utilities Commission to reassess the compensation framework, resulting in a 2022 tariff that significantly reduced payments for customer-generated power. Environmental groups challenged the new tariff, arguing it failed to account for all societal benefits of renewable energy and did not adequately promote growth among disadvantaged communities.The First Appellate District, Division Three, reviewed the challenge after the petitioners sought a writ of review. The Court of Appeal affirmed the Commission’s decision, applying a highly deferential standard from Greyhound Lines, Inc. v. Public Utilities Com., which upheld Commission interpretations unless they lacked a reasonable relation to statutory purposes and language. The appellate court concluded that the Commission’s approach met this deferential standard and declined to engage in further inquiry.The Supreme Court of California granted review to determine whether the deferential Greyhound standard remains appropriate following legislative amendments to the Public Utilities Code. The Supreme Court held that, due to statutory changes in the 1990s and 2000s, the Greyhound standard no longer applies to most Commission decisions, including those involving energy. Instead, courts must now independently review the Commission’s statutory interpretations, consistent with the approach outlined in Yamaha Corp. of America v. State Bd. of Equalization. The Supreme Court reversed the Court of Appeal’s judgment and remanded the case for further proceedings under the correct standard of review. View "Center for Biological Diversity, Inc. v. Public Utilities Com." on Justia Law
Posted in:
Supreme Court of California, Utilities Law
Delta Air Lines, Inc. v. Dept. of Revenue
The case involves Delta Air Lines, Inc. and PacifiCorp, both of which are centrally assessed businesses in Oregon. Under Oregon law, centrally assessed businesses are taxed on their intangible property, unlike locally assessed businesses. Delta and PacifiCorp challenged this tax, arguing it violated the state and federal constitutions by not being uniform and by violating equal protection and privileges clauses.The Oregon Tax Court addressed both cases in a single opinion, ruling in favor of Delta by finding the tax on intangible property unconstitutional for air transportation businesses. However, it ruled against PacifiCorp, upholding the tax for utilities. The Tax Court concluded that there were no genuine differences between the intangible property of centrally assessed air transportation businesses and locally assessed businesses, but found differences for utilities.The Oregon Supreme Court reviewed the case, focusing on whether the tax classifications were rationally related to a legitimate governmental purpose. The court reversed the Tax Court's decision regarding Delta, holding that the tax on intangible property for centrally assessed businesses is constitutional. The court found that the legislature's decision to tax intangible property of centrally assessed businesses, but not locally assessed ones, was rationally related to legitimate purposes such as administrative efficiency, expertise in valuation, and balancing revenue against resources. The court also affirmed the Tax Court's decision regarding PacifiCorp in a separate opinion, maintaining the tax's constitutionality for utilities. The case was remanded to the Tax Court for further proceedings. View "Delta Air Lines, Inc. v. Dept. of Revenue" on Justia Law
Florida Rising, Inc. v. Florida Public Service Commission
Florida Power & Light Company (FPL) entered into a multi-party settlement agreement to establish base rates, which was approved by the Florida Public Service Commission (Commission). The settlement allowed FPL to increase rates annually for four years, generating significant additional revenue and permitting incremental rate increases for solar projects. It also included provisions for an equity-to-debt ratio, return on equity, and a minimum base bill for customers. The settlement aimed to support investments in power generation, transmission, distribution systems, and renewable energy programs.The Commission's initial approval of the settlement was challenged, leading to a remand by the Supreme Court of Florida in Floridians Against Increased Rates, Inc. v. Clark (FAIR). The Court required the Commission to provide a more detailed explanation of its reasoning and to consider FPL's performance under the Florida Energy Efficiency and Conservation Act (FEECA). On remand, the Commission denied a motion to reopen the evidentiary record and issued a Supplemental Final Order, reaffirming that the settlement was in the public interest.The Supreme Court of Florida reviewed the case again. The Court upheld the Commission's approval of the settlement, finding that the Commission's factual findings were supported by competent, substantial evidence and that its policy decisions were within its discretion. The Court concluded that the Commission had adequately considered the mandatory and discretionary factors, including FPL's FEECA performance, and provided a reasoned explanation for its decision. The Court affirmed the Commission's Final and Supplemental Final Orders, determining that the settlement established fair, just, and reasonable rates. View "Florida Rising, Inc. v. Florida Public Service Commission" on Justia Law