Justia Utilities Law Opinion Summaries

Articles Posted in Environmental Law
by
DTE's Monroe plaint is the largest coal-fired power plant in Michigan; in 2010, DTE undertook a $65 million overhaul. The day before construction began, DTE submitted notice to the Michigan Department of Environmental Quality stating that DTE predicted an increase in post-construction emissions 100 times greater than the minimum necessary to constitute a “major modification” and require a preconstruction permit. DTE characterized the projects as routine maintenance,exempt from New Source Review (NSR) under the Clean Air Act, 42 U.S.C. 7475, 7503, and stated that it had excluded the entire predicted emissions increase from its projections of post-construction emissions based on “demand growth.” DTE began construction without an NSR permit. The EPA filed suit. In 2013, the Sixth Circuit held that a utility seeking to modify a source of air pollutants must “make a preconstruction projection of whether and to what extent emissions from the source will increase following construction,” which “determines whether the project constitutes a ‘major modification’ and thus requires a permit.” On remand, the district court again entered summary judgment for DTE, concluding that the EPA had to accept DTE’s projections at face value. The Sixth Circuit reversed. DTE was not required to secure the EPA’s approval of the projections, or the project, before construction, but in proceeding without a permit, DTE acted at its own risk. The EPA can challenge DTE’s preconstruction projections and there are genuine disputes of material fact that preclude summary judgment regarding compliance with NSR’s preconstruction requirements. The court noted that construction is complete and that actual post-construction emissions are irrelevant o whether DTE’s preconstruction projections complied with the regulations. View "United States v. DTE Energy Co." on Justia Law

by
Panoche, a producer of electricity, and Pacific Gas and Electric Company (PG&E), a utility that purchases its electricity, disputed which of them should bear the costs of complying with a legislatively-mandated program to reduce greenhouse gas emissions pursuant to the Global Warming Solutions Act (Assem. Bill 32 (2005–2006 Reg. Sess.). PG&E invoked the arbitration clause in its agreement with Panoche. Panoche resisted arbitration, arguing that the controversy was not ripe for resolution because ongoing regulatory proceedings at the California Air Resources Board and the California Public Utilities Commission would at least provide guidance in the arbitration and could render the proceeding unnecessary. The arbitration panel denied Panoche’s motion, and after a hearing determined that Panoche had assumed the cost of implementing AB 32 under the agreement and understood that at the time of signing. The arbitrators also concluded that the parties “provide[ed] for recovery of GHG costs” by Panoche through a “payment mechanism” in the agreement. The trial court agreed with Panoche, ruled that the arbitration was premature, and vacated the award. The court of appeal reversed and ordered confirmation of the award. Panoche identified no procedural disadvantage it suffered in going forward with the arbitration as scheduled and failed to meet the “sufficient cause” prong under Code of Civil Procedure 1286.2(a)(5). View "Panoche Energy Ctr. v. Pac. Gas & Elec." on Justia Law

by
Great Oaks, a water retailer, challenged a groundwater extraction fee imposed on water it draws from wells on its property. The power to impose such a fee is statutorily vested in the Santa Clara Valley Water Management District. The trial court awarded a refund of charges paid by Great Oaks, finding that the charge violated the provisions of both the District Act and Article XIII D of the California Constitution, which imposes procedural and substantive constraints on fees and charges imposed by local public entities. The court of appeal reversed, holding that the fee is a property-related charge for purposes of Article 13D, subject to some constraints, but is also a charge for water service, exempt from the requirement of voter ratification. A pre-suit claim submitted by Great Oaks did not preserve any monetary remedy against the District for violations of Article 13D and, because the matter was treated as a simple action for damages when it should have been treated as a petition for a writ of mandate, the trial court failed to apply a properly deferential standard of review to the question whether the District’s setting of the fee, or its use of the resulting proceeds, complied with the District Act. View "Great Oaks Water Co. v. Santa Clara Valley Water Dist." on Justia Law

by
Citizens of Myersville, in Frederick County, Maryland, oppose the construction of a natural gas facility called a compressor station in their town as part of a larger expansion of natural gas facilities in the northeastern United States proposed by Dominion, a regional natural gas company. The Federal Energy Regulatory Commission, over the objections of the citizens, conditionally approved it. Dominion fulfilled the Commission’s conditions, including obtaining a Clean Air Act permit from the Maryland Department of the Environment. Dominion built the station, and it has been operating for approximately six months. The D.C. Circuit denied a petition for review, rejecting arguments that the Commission lacked substantial evidence to conclude that there was a public need for the project; that the Commission unlawfully interfered with Maryland’s rights under the Clean Air Act; that environmental review of the project, including its consideration of potential alternatives, was inadequate; and that the Commission unlawfully withheld hydraulic flow diagrams from them in violation of their due process rights. View "Myersville Citizens for a Rural Community, Inc. v. Fed. Energy Regulatory Comm'n" on Justia Law

by
The State Corporation Commission issued to Virginia Electric and Power Company certificates of public convenience and necessity authorizing the construction of electric transmission facilities. BASF Corporation appealed, challenging the approval of the transmission line’s route across an environmental remediation site on its property along the James River. James City County, Save the James Alliance Trust, and James River Association (collectively, JCC) also appealed, challenging the approval of an overhead transmission line that will cross the James River and a switching station that will be located in James City County. The Supreme Court affirmed in part and reversed in part, holding (1) the Commission did not err in its construction or application of Va. Code 56-46.1’s requirements that the power company reasonably minimize adverse environmental impacts on the area concerned, and the Commission’s findings were not contrary to the evidence or without evidentiary support; and (2) the Commission erred in concluding that the switching station was a “transmission line” under Va. Code 56-46.1(F) and therefore not subject to local zoning ordinances. Remanded as to the JCC appellants. View "BASF Corp. v. State Corp. Comm’n" on Justia Law

by
Petitioners challenged the Commission's approval of a proposal for the construction of a natural gas compressor station in the Town of Minisink, New York. Petitioners argued, among other things, that the Commission's approval of the project was arbitrary and capricious, particularly given the existence of a nearby alternative site (the Wagoner Alternative) they insist is better than the Minisink locale. The court concluded that the Commission's consideration of the Wagoner Alternative falls within the bounds of its discretion and the court had no basis to upset the Commission's application of its Section 7 of the Natural Gas Act, 15 U.S.C. 717-717z, authority on this point; the court was satisfied that the Commission properly considered cumulative impacts of the Minisink Project; the court reject petitioners' argument that the Minisink Project violates the siting guidelines; and the court rejected petitioners' claims of procedural errors. Accordingly, the court denied the petitions for review. View "Minisink Residents for Enviro., et al. v. FERC" on Justia Law

by
Portland Generating Station is a 427-megawatt, coal-fired, electricity generating plant in Northampton County, Pennsylvania, directly across the Delaware River within 500 feet of Warren County, New Jersey. The EPA found that Portland emits sulfur dioxide in amounts that significantly interfere with control of air pollution across state borders. In response to a petition under the Clean Air Act (42 U.S.C. 7408, 7409)), the EPA imposed direct limits on Portland‘s emissions and restrictions to reduce its contribution to air pollution within three years. The Third Circuit upheld the EPA actions. It was reasonable for the EPA to interpret Section 126(b) as an independent mechanism for enforcing interstate pollution control, giving it authority to promulgate the Portland Rule. The contents of the Portland Rule are not arbitrary, capricious, or abusive of the EPA‘s discretion. View "GenOn REMA LLC v. U.S. Envtl. Prot. Agency" on Justia Law

by
Between 1994 and 1999 Commonwealth Edison modified five Illinois coal-fired power plants that had been operating on August 7, 1977, and were, therefore, grandfathered against a permitting requirement applicable to any “major emitting facility” built or substantially modified after that date in parts of the country subject to the rules about prevention of significant deterioration, 42 U.S.C. 7475(a), until the modification. The permit requires installation of “the best available control technology for each pollutant subject to regulation.” Commonwealth Edison did not obtain permits. There was no challenge until 2009, a decade after completion of the modifications. The district court dismissed a challenge as untimely. After finishing the modifications, Commonwealth Edison sold the plants to Midwest. The federal government and Illinois (plaintiffs) argued that the district court allowed corporate restructuring to wipe out liability for ongoing pollution. Midwest and its corporate parent (Edison Mission) filed bankruptcy petitions after the appeal was argued. The Seventh Circuit affirmed. Midwest cannot be liable because its predecessor would not have been liable had it owned the plants continuously. Commonwealth Edison needed permits before undertaking the modifications. The court rejected arguments of continuing-violation and continuing-injury. View "United States v. Midwest Generation, LLC" on Justia Law

by
Intervenor, Sunflower Electric Power Corporation, appealed the grant of summary judgment to the Sierra Club based on violations of the National Environmental Policy Act (NEPA), 42 U.S.C. 4321 et seq., by the USDA's Rural Utilities Services. The district court ruled that the Service unlawfully failed to prepare an environmental impact statement (EIS) before granting approvals and financial assistance to Sunflower's expansion of its coal-fired power plant, and remanded the matter to the Service, enjoining it from granting further approvals until it completed an EIS. The court dismissed the appeal for lack of jurisdiction under 28 U.S.C. 1291 because Sunflower appealed a non-final remand order that was not immediately appealable by a private party and under section 1292(a)(1) because the injunction served no purpose beyond the remand. View "Sierra Club v. U.S. Dept. of Agriculture, et al" on Justia Law

by
In this appeal, Appalachian Power Company (APCO) sought rate adjustment clause recovery of $33.3 million in environmental compliance costs that the State Corporation Commission denied. The Supreme Court reversed in part, affirmed in part, and remanded, holding (1) APCO was entitled to a rate adjustment clause for recovery of actual costs it directly incurred for environmental compliance in 2009 and 2010 but did not recover through its base rates, and the portion of the Commission's decision denying recovery of environmental compliance costs on the basis that those costs were connected with projects included in APCO's base rates which APCO had the opportunity to recover was reversed; and (2) the portion of the Commission's decision denying APCO recovery of environmental compliance costs alleged to be embedded in the capacity equalization charges APCO paid to its affiliates in 2009 and 2010 was affirmed. Remanded. View "Appalachian Power Co. v. State Corp. Comm'n" on Justia Law