Justia Utilities Law Opinion Summaries
Articles Posted in Energy, Oil & Gas Law
In re Application of Suburban Natural Gas Co.
The Supreme Court reversed the decision of the Public Utilities Commission of Ohio (PUCO) allowing a gas company to charge its customers higher rates, holding that the PUCO erred by approving the rate increase.At issue was whether Suburban Natural Gas Company's customers must pay for a 4.9-mile extension of the company's pipeline. The PUCO determined that the pipeline extension met the "used-and-useful" test as of a specified date and approved the rate increase. See Ohio Rev. Code 4909.15(A)(1). The Supreme Court reversed, holding (1) the PUCO looked beyond whether the entire 4.9-mile extension was used and useful on the applicable date and considered whether it was a prudent investment because it might prove useful in the future; and (2) therefore, the PUCO erred in evaluating the rate increase. View "In re Application of Suburban Natural Gas Co." on Justia Law
In re Petition of Portland Street Solar LLC
Portland Street Solar LLC appealed a Public Utility Commission order denying Portland Street’s petition for a certificate of public good (CPG) to install and operate a 500-kW solar group net-metering system adjacent to a previously permitted solar array owned by Golden Solar, LLC. Interpreting the definition of “plant” set forth in 30 V.S.A. 8002(18), the Commission determined that the proposed Portland Street project would be part of a single plant along with the already-approved adjacent Golden Solar project and thus would exceed the 500-kw energy-generating-capacity limit applicable in the net-metering program. On appeal, Portland Street argued the Commission’s decision was inconsistent with the Vermont Supreme Court’s controlling precedent, as well as prior Commission decisions involving similar cases, and that the Commission exceeded its statutory authority by expansively construing the component parts of section 8002(18) that defined the characteristics of a single plant. Applying the appropriate deferential standard of review, the Supreme Court concluded the Commission’s self-described expanded and refined interpretation of what constituted a single plant under section 8002(18) was not arbitrary, unreasonable, or discriminatory and did not amount to compelling error that would require the Court to intervene in matters the Legislature has delegated to the Commission’s expertise. Accordingly, the Court affirmed the Commission’s decision denying Portland Street’s petition for a CPG to install and operate its proposed facility under the net-metering program. View "In re Petition of Portland Street Solar LLC" on Justia Law
Oklahoma Gas and Electric Co. v. Federal Energy Regulatory Commission
Several utilities that are managed by the Southwest Power Pool (SPP), a regional transmission operator, paid for upgrades to the transmission grid. The operative tariff required other utilities who benefitted from these upgrades to share the costs of the expanded network. The tariff, however, also required SPP to invoice the charges monthly and to make adjustments within one year. The reimbursement calculation proved complicated. It took SPP eight years to implement it, during which time SPP did not invoice for the upgrade charges. FERC initially granted SPP a waiver of the tariff’s one-year time bar but later determined it lacked the authority to waive this provision retroactively. FERC’s revised determination meant the utilities that had made substantial outlays for upgrades were denied reimbursement for the eight years that had elapsed.The D.C. Circuit denied petitions for review filed by SPP and a company that sponsored upgrades and has been denied reimbursement. Once a tariff is filed, FERC has no statutory authority (16 U.S.C. 824d(d)) to provide equitable exceptions or retroactive modifications to the tariff. SPP may impose only those charges contained in the filed rate. Because the one-year time bar for billing is part of the filed rate, FERC could not retroactively waive it, even to remedy a windfall for users of the upgraded networks. View "Oklahoma Gas and Electric Co. v. Federal Energy Regulatory Commission" on Justia Law
Louisiana Public Service Commission v. Federal Energy Regulatory Commission
Entergy, a public utility holding company, owns five operating companies that sell electricity in four states, including Louisiana. The companies have been governed by an agreement requiring them to act as a “single economic unit” and requiring “rough equalization” of their production costs. In 2005, the Federal Energy Regulatory Commission (FERC) determined that the production costs were not roughly equal and imposed a “bandwidth remedy”: Whenever the yearly production costs of an individual operating company deviated from the average by more than 11%, companies with lower costs were required to pay companies with higher costs as necessary to bring all five companies within that range. Entergy filed a tariff establishing a formula to calculate production costs subject to the bandwidth remedy, which FERC largely accepted.Utilities often spread their recovery of large, non-recurring costs by creating a regulatory asset, a type of credit. The company then amortizes the asset in later years, creating debits chargeable to customers. Historically, the Entergy companies recorded regulatory assets and their related amortization expenses in FERC accounts not referenced in the bandwidth formula; this effectively accounted for deferred production costs when they were incurred, rather than when the related amortization expenses were recorded. FERC rejected that approach and excluded purchased-power costs that a Louisiana affiliate incurred in 2005 and amortized in 2008 and 2009.The D.C. Circuit denied the Louisiana Public Service Commission’s petition for review. The Federal Power Act requires electric utilities to charge “just and reasonable” rates. 16 U.S.C. 824d(a). If FERC finds a rate unreasonable, it may establish a just and reasonable rate; FERC may reallocate production costs under the Entergy system agreement, including by ensuring compliance with the bandwidth remedy. View "Louisiana Public Service Commission v. Federal Energy Regulatory Commission" on Justia Law
In re Application of Hawaiian Electric Co.
The Supreme Court held that the Public Utilities Commission (PUC) did not abuse its discretion in deciding not to reopen a December 2014 order (Order No. 32600) upon allegations raised in 2019 that changed circumstances warranted relief from the order.The order at issue approved a purchase power agreement (PPA) in which Hawaiian Electric Company agreed to purchase wind energy generated by Na Pua Makani on a wind farm to be constructed on the island of O'ahu. Life of the Land (LOL) sought to reopen the order with reference to Hawai'i Rules of Civil Procedure Rule 60(b). The PUC denied LOL's motion for relief, concluding that it was without jurisdiction to consider the motion because LOL had not timely appealed the order under Haw. Rev. Stat. 269-15.5 and, alternatively, that the motion for relief was an untimely motion for rehearing or reconsideration. The Supreme Court affirmed, holding that the PUC did not abuse its discretion in declining to turn to HRCP Rule 60(b) to reopen Order No. 32600. View "In re Application of Hawaiian Electric Co." on Justia Law
PennEast Pipeline Co. v. New Jersey
Under the Natural Gas Act, to build an interstate pipeline, a natural gas company must obtain from the Federal Energy Regulatory Commission (FERC) a certificate of "public convenience and necessity,” 15 U.S.C. 717f(e). A 1947 amendment, section 717f(h), authorized certificate holders to exercise the federal eminent domain power. FERC granted PennEast a certificate of public convenience and necessity for a 116-mile pipeline from Pennsylvania to New Jersey. Challenges to that authorization remain pending. PennEast sought to exercise the federal eminent domain power to obtain rights-of-way along the pipeline route, including land in which New Jersey asserts a property interest. New Jersey asserted sovereign immunity. The Third Circuit concluded that PennEast was not authorized to condemn New Jersey’s property.The Supreme Court reversed, first holding that New Jersey’s appeal is not a collateral attack on the FERC order. Section 717f(h) authorizes FERC certificate holders to condemn all necessary rights-of-way, whether owned by private parties or states, and is consistent with established federal government practice for the construction of infrastructure, whether by government or through a private company.States may be sued only in limited circumstances: where the state expressly consents; where Congress clearly abrogates the state’s immunity under the Fourteenth Amendment; or if it has implicitly agreed to suit in “the structure of the original Constitution.” The states implicitly consented to private condemnation suits when they ratified the Constitution, including the eminent domain power, which is inextricably intertwined with condemnation authority. Separating the two would diminish the federal eminent domain power, which the states may not do. View "PennEast Pipeline Co. v. New Jersey" on Justia Law
Environmental Defense Fund v. Federal Energy Regulatory Commission
Spire planned to build a St. Louis-area pipeline and unsuccessfully solicited natural gas “shippers” to enter into preconstruction “precedent agreements.” Spire later entered into a precedent agreement with its affiliate, Spire Missouri, for 87.5 percent of the pipeline’s projected capacity. Spire applied to the Federal Energy Regulatory Commission (FERC) for a certificate of public convenience and necessity (Natural Gas Act, 15 U.S.C. 717f(c)(1)(A)), conceding that the proposed pipeline was not needed to serve new load but claiming other benefits. As evidence of need, Spire relied on its precedent agreement with Spire Missouri. FERC released an Environmental Assessment, finding no significant environmental impact. EDF challenged Spire’s application, arguing that the precedent agreement should have limited probative value because the companies were corporate affiliates. The Order approving the new pipeline principally focused on the precedent agreement.The D.C. Circuit vacated the approval. FERC may issue a Certificate only if it finds that construction of a new pipeline “is or will be required by the present or future public convenience and necessity.” Under FERC’s “Certificate Policy Statement,” if there is a need for the pipeline, FERC determines whether there will be adverse impacts on existing customers, existing pipelines, or landowners and communities. If adverse stakeholder impacts will result, FERC balances the public benefits against the adverse effects. FERC’s refusal to address nonfrivolous arguments challenging the probative weight of the affiliated precedent agreement did not evince reasoned and principled decision-making. FERC ignored evidence of self-dealing and failed to thoroughly conduct the interest-balancing inquiry. View "Environmental Defense Fund v. Federal Energy Regulatory Commission" on Justia Law
In re Hawai’i Electric Light Co.
The Supreme Court vacated two orders of the Public Utilities Commission (PUC) denying a competitive bidding waiver to Hawai'i Electric Light Company, Inc. (HELCO) and denying Hu Honua's request for reconsideration of the first order, holding that both orders were the result of a misreading of the holding in Matter of Hawai'i Electric Light Co., 445 P.3d 673 (Haw. 2019) (HELCO I).In 2017, the PUC granted HELCO a waiver from competitive bidding for a proposed power purchase agreement HELCO wanted to enter into with Hu Honua (the amended PPA). The 2017 waiver was issued alongside the PUC's approval of the amended PPA. The Supreme Court vacated the decision and remanded for further proceedings. On remand, the PUC issued Order No. 37205 denying HELCO's request for a waiver under the belief that HELCO I nullified the 2017 waiver. In order No. 37306, the PUC denied Hu Honua's request for reconsideration. The Supreme Court reversed, holding that HELCO I did not vacate the 2017 waiver and, by extension, did not require the PUC to revisit the threshold waiver issue. View "In re Hawai'i Electric Light Co." on Justia Law
Public Service Electric and Gas Co. v. Federal Energy Regulatory Commission
In 2016, the Federal Energy Regulatory Commission approved, as just and reasonable, cost allocations filed by PJM, the Mid–Atlantic’s regional transmission organization, for a project to improve the reliability of three New Jersey nuclear power plants. The Commission denied a complaint lodged by Delaware and Maryland alleging a large imbalance between the costs imposed on the Delmarva transmission zone and the benefits that zone would accrue from the project. On rehearing in 2018, the Commission reversed course, concluding that application of PJM’s cost–allocation method to the project violated cost–causation principles and was therefore unjust and unreasonable under the Federal Power Act, 16 U.S.C. 824e. The Commission’s replacement cost–allocation method shifted primary cost responsibility for the project from the Delmarva zone to utilities in New Jersey.The New Jersey Agencies argued that the Commission departed from precedent without adequate explanation, made findings that are unsupported by substantial evidence, and failed to respond meaningfully to objections raised during the proceedings. The D.C. Circuit denied their petitions for review. The Commission reasonably decided to adopt a different cost–allocation method for the type of project at issue here and adequately explained its departure from the cost allocations it had approved in 2016. View "Public Service Electric and Gas Co. v. Federal Energy Regulatory Commission" on Justia Law
Communities for a Better Environment v. Energy Resources Conservation & Development Commission
Environmental groups challenged the constitutionality of Public Resources Code section 25531, which limits judicial review of decisions by the Energy Resources Conservation and Development Commission on the siting of thermal power plants. Section 25531(a) provides that an Energy Commission siting decision is “subject to judicial review by the Supreme Court of California.” The plaintiffs contend this provision abridges the original jurisdiction of the superior courts and courts of appeal over mandate petitions, as conferred by California Constitution Article VI, section 10. Section 25531(b) provides that findings of fact in support of a Commission siting determination “are final,” allegedly violating the separation of powers doctrine by depriving courts of their essential power to review administrative agency findings (Cal. Const., Art. III, section 3; Art. VI, section 1).The court of appeal affirmed summary judgment in favor of the plaintiffs. The Article VI grant of original jurisdiction includes the superior courts and courts of appeal and may not be circumscribed by statute, absent some other constitutional provision. Legislative amendments to section 25531 have broken the once-tight link between the regulatory authority of the Public Utilities Commission (PUC) and Energy Commission power plant siting decisions, such that the plenary power Article XII grants the Legislature over PUC activities no longer authorizes section 25531(a). Section 25531(b) violates the judicial powers clause by preventing courts from reviewing whether substantial evidence supports the Commission’s factual findings. View "Communities for a Better Environment v. Energy Resources Conservation & Development Commission" on Justia Law