Ameren Services Co. v. FERC

by
FERC issued a series of orders empowering incoming generators within the Midcontinent Independent System Operator (MISO) region to elect to self-fund this new construction, or to seek financing from third parties, regardless of whether the current grid owners wish to fund the construction themselves. The DC Circuit vacated the orders, holding that there was neither evidence nor economic logic supporting FERC's discriminatory theory as applied to transmission owners without affiliated generation assets. The court also held that FERC did not adequately respond to petitioners' argument that involuntary generator funding compelled them to construct, own, and operate facilities without compensatory network upgrade charges – thus forcing them to accept additional risk without corresponding return as essentially non-profit managers of these upgrade facilities. Accordingly, the court remanded for further proceedings. View "Ameren Services Co. v. FERC" on Justia Law